A "Pre-Submission" conference was held with the Thurston County Development Services Division to obtain information on the requirements which will need to be met when applying for the construction permit. This conference was attended by Park Association President, Mary Lewis; Park Architect, Markthor MacFarlane; and Rochester School District Representative, Larry Quarnstrom from the Grand Mound Rochester Park Association (GMRPA) and the various county employee's involved in the permitting process.
A physical survey of the property has been now completed. This step was necessary to establish the exact boundary lines for the park. The next step in this process is for GMRPA to super-impose these boundary lines onto the park design drawing. The drawing which many of you have seen was hand drawn and will need to be re-created as a digitized (computerized) version of the drawing. Some very minor changes may occur to conform to the property boundaries but all basic elements will remain on the proposed plan. Markthor is currently working on this task.
New Item Bids were solicited and are now being evaluated for the construction of the walking path around the perimeter of the park. It is anticipated the paving will be complete by early summer. Plans are also being formulated for building two half-court basketball , horseshoe pit and tether-ball areas along with a couple of benches. Completion of these items is also expected by early summer.
The GMRPA has been busy during the past 1 ˝ years.
Itemized below is a list of these accomplishments.
2005
April - voted in new officers | |
May - Added park information link to the community calendar website | |
June - Hosted a booth at the Swede Day Parade, canvassing residents to complete a park survey that would be used to help design the park. | |
August - Hosted the first annual “Sleep In The Park”, Community Campout & Barbeque | |
September - Worked with United Way Day of Caring to prime the existing playground equipment | |
October - Worked with AmeriCorps to colorfully paint the playground equipment | |
November - Booth at the community health fair at the Middle School | |
December - Assisted in hosting the Christmas Tree Lighting at the community center | |
July - Dec., 2005 - Developed three different concepts for the park design; worked with Thurston County Development Services in preparing for the permitting process |
2006
January - Approved plans for the park concept | |
January through April - Met with various community groups to present the concept and to gain community input and support | |
March - Hosted first annual “Flashlight Easter Egg Hunt” for Middle School students. | |
March - Submitted funding request to STEPS, Thurston County Public Health | |
April - Elections were held for Officers and directors of the board. The board now consists of four officers and 5 directors. | |
May - Met with Development Services to begin permit process | |
June - Swede Day booth, Membership campaign begins | |
July - Preliminary design for a Grand Mound Rochester Park Association Logo developed | |
August – Second Annual “Sleep In The Park” scheduled for the 12th & 13th of August | |
December - Hosted "Breakfast with Santa" at the Rochester High School | |
December - Hosted "2nd Annual Community Christmas Tree Lighting" and fellowship at the Community Center |
2007
May - Two park benches were constructed by Rochester High School Shop classes | |
June - Walking path base gravel placed by Martin Sand & Gravel and paved by PaveX | |
June - Base gravel and paving for two half-court basketball courts placed by Martin Sand & Gravel and paved by PaveX | |
June - Gates repaired at both end of Bend Street side of Park fence to prevent people from driving upon the walking path. | |
June - Volunteer work crew poured concrete bases for three picnic tables and two benches. These will be installed in late June after the concrete has had time to cure properly |
2008
May - Comcast Cares Day saw the construction of several more benches, erection of the two basketball hoops, installation of the three barbeque pits and the two horseshoe pits. Flower beds were enhanced with new bark dust after being weeded, Some new boards were installed on the swing/slide surround. An American Flag was painted on the south end of the building at the east side of the park. | |
June - (Sadly, the steel pins in the horseshoe pits have been stolen and now all the picnic tables have been destroyed by vandals) | |
September - The construction of the covered shelter is waiting on Thurston County approval of the permit to build it. | |
November - Construction of the "Community Gardens" beds along the west side of the park. This is a collation of ROOF, WSU Master Gardeners, 4-H, GRUB (Garden Raised Bounty), Rochester Water Association, Rochester School District, and the Grand Mound Rochester Park Association as the lead organization. Click here to view pictures of this activity. |
2009
February - Constructed raised beds and filled them with soil for the Rochester Community Gardens | |
March - Built a tool shed for the Rochester Community Gardens | |
June - Installed chain-link fencing around Rochester Community Gardens | |
July - Grand Mound Rochester Chamber of Commerce donated three wooden picnic tables | |
July - Purchased and planted three Red Leaf Maples trees bringing the total trees in the park to six | |
July - "Fun Day in the Park" with hot dogs and games for all ages |